Construction Management Online Test – Multiple Choice Questions and Answers 1. The main advantage of line organisation, is : rigid discipline in the organisation ability of quick decision at all levels defined responsibilities at all level All 2. Power stations are generally treated as industrial construction electrical construction heavy construction light construction 3. Railway projects are treated as light construction industrial construction heavy construction none of these 4. Pre-tender stage requires selection of site fmalisation of alignment of work fmalisation of designs and preparation of estimate All 5. For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is 1 2 3 4 6. Pick up the correct statement from the following The critical path consumes the maximum time The activities connecting the events having zero slack, lie on the critical path The difference of latest occurence time and earliest expected time, is called slack All 7. Pick up the correct statement from the following: Optimistic time estimate refers to activities Pessimistic time estimate refers to activities Most likely time estimate refers to activities All 8. The final selection of a construction site, is done by representative of engineer authority local civil authority representative representative of administration All 9. The main disadvantage of line organisation, is rigid structure top level executions over work extraordinary delay in communications All 10. PERT is limited of event oriented diagrams based on three time estimates for activities linking up two events used for research and development projects All Loading … Question 1 of 10