1. What is short form of Finish Start?
a. AS
b. LS
c. FF
d. FS
Answer: d

2.What is short form of Earliest Finis ?
a. AF
b. EF
c. ES
d. TF
Answer: b

3.Which one is involved in Overall Network Scheduling Transaction with selection options?
a. REL
b. CN24N
c. TF
d. PDC
Answer: b

4.Object representing events that are particularly important for the progress of the project or are of special interest. You can assign milestones to individual activities or WBS elements by using ________
a. Milestones
b. SS
c. Reduction
d. LS
Answer:a

5. Controls how actual dates from partial confirmations affect further scheduling runs in PLM ?
a. Project Definition
b. Shift Order Indicator
c. Sales Order
d. What is an activity?
Answer: b

6.A model of the project that shows the project activities to be fulfilled in the hierarchical form. It divides the project into clearly-structured sections means?
a. Forward Scheduling
b. What is an activity?
c. Work Breakdown Structure (WBS)
d. Backward Scheduling
Answer: c

7.Production Order means?
a. Comparison or evaluation of data?
b. What period will be evaluated?
c. A production order used in discrete manufacturing.
d. CJ29 – Project Scheduling Transaction
Answer: c

8. Which one is entered in networks using confirmations.?
a. Internal Order
b. Actual Dates
c. Claim
d. Cost Center
Answer: b

9.What is mean by Purchase Order in PLM ?
a. A request or instruction from a purchasing organization to a vendor (external supplier) or a plant to deliver a quantity of material or render a service at a certain point in time.
b. Overall Network Scheduling Transaction with selection options
c. The smallest organization unit within a company, used to represent a closed system for cost accounting purposes. A controlling area may include single or multiple company codes that may use different currencies.
d. A request or instruction to Purchasing to procure a quantity of a material or service so what it is available at a certain point in time.
Answer: a

10.Which one is called “An organizational unit within a controlling area that represents a defined location of cost incurrence. The definition can be based on functional requirements, allocation criteria, physical locations or responsibility for costs”.?
a. Company Code”
b. Profit Center
c. Actual Dates
d. Cost Center
Answer: d

SAP PLM Objective Questions
SAP PLM MCQs

11.What is mean by “The network structures that are not directly associated with a project and can be used as templates for creating other standard networks or operative networks”.?
a. Standard Network
b. Network
c. Customer Inquiry
d. Budget
Answer:a

12.What is mean by “a customer request to a company for a quotation or sales information that is not binding. The request is received by a sales area that is then responsible for processing it further”.?
a. Goods Issue
b. Customer Inquiry
c. Cost Center
d. Control profile
Answer: b

13.which one is Used to set control keys.?
a. SS
b. AF
c. OSPU
d. SF
Answer:c

14.which one isDetermines the latest dates
a. Forward Scheduling
b. Purchasing
c. Backward Scheduling
d. Work Center
Answer: c

15.What is Determines the earliest dates means?
a. Company Code
b. Forward Scheduling
c. Work Center
d. Scheduling type
Answer: b

SAP PLM Objective type Questions with Answers

16.What is mean by a request or instruction to Purchasing to procure a quantity of a material or service so what it is available at a certain point in time.?
a. Purchase Order
b. Project Definition
c. Purchase Requisition
d. Cost Center
Answer: c

17.An organizationl unit that defines where and by whom an activity is to be carried otu. The data in the work center can be used for scheduling, costing, and capacity planning means?
a. Profit Center
b. Work Center
c. Cost Center
d. WBS Element
Answer: b

18.Which requirements do you want to display?
a. Period profile
b. Evaluation profile
c. Selection profile
d. Production Order
Answer: b

19. A neutral work breakdown structure that can be used several times over and only serves as a template for creating operative work breakdown structures means?
a. Standard Network
b. Work Breakdown Structure (WBS)
c. Standard Work Breakdown Structure
d. Work Center
Answer: c

20. Order for detailed planning and associated documetnation of measures during maintenance means?
a. Purchase Order
b. Sales Order
c. Maintenance Order
d. Internal Order
Answer: c

21.What is mean by Purchasing in PLM ?
a. A term from Inventory Management denoting a physical inward movement of goods or material from a company, usally with reference to a purchase order or production order.
b. A component of Materials Management with the following tasks; procuring materials and services externally, determining possible sources of supply for a requirement, monitoring goods deliveries and payment.
c. A request or instruction to Purchasing to procure a quantity of a material or service so what it is available at a certain point in time.
d. Overall Network Scheduling Transaction with selection options
Answer: b

22. CNF means?
a. Finish Start
b. Finish Finish
c. Finally Confirmed
d. Earliest Finish
Answer: c

23. PDC means?
a. Plant Data Collection
b. Total Float
c. Start Start
d. Actual Start Date

24. What is Factors influencing Scheduling?
a. CJ29 – Project Scheduling Transaction
b. Are entered in networks using confirmations.
c. Internal Processing External Processing General Costs Activity
Relationships
d. Internal processing External processing costs service
Answer: c

25.A request or instruction to Purchasing to procure a quantity of a material or service so what it is available at a certain point in time.?
a. Project Definition
b. Purchase Order
c. Purchase Requistion
d. Purchasing
Answer: c

26. An organizational unit in Accounting that reflects a management-oriented structure fo the organization for the purpose of internal control.?
a. WBS Element
b. Profit Center
c. Work Center
d. Project Definition
Answer: b

27. The smallest organization unit within a company, used to represent a closed system for cost accounting purposes. A controlling area may include single or multiple company codes that may use different currencies.?
a. Control profile
b. Company Code
c. CNF
d. BOM
Answer: b

28. A production order used in discrete manufacturing.?
a. Production Order
b. Profit Center
c. Sales Order
d. Purchase Order
Answer: a

29. Comparison or evaluation of data?
a. Selection profile
b. Control profile
c. List Profile
d. Time profile
Answer: b

30. Object representing events that are particularly important for the progress of the project or are of special interest. You can assign milestones to individual acitvities or WBS elements.?
a. ES
b. Network
c. Reduction
d. Milestones
Answer: d