250+ TOP MCQs on Types of Estimates and Answers

Construction Cost Estimation Multiple Choice Questions & Answers (MCQs) on “Types of Estimates”.

1. Which of the following data is not required to prepare an estimate?
a) Amplitude
b) Drawings
c) Specifications
d) Rates

Answer: a
Clarification: For preparing an estimate, data such as drawings, detailed specifications, rates, etc. is required. The drawings needed to prepare the estimate include plans, sections, elevations, etc.

2. Estimating is the technique of calculating the various quantities and is needed for controlling the expenditure during the execution of the work.
a) True
b) False

Answer: a
Clarification: Estimating is the process of calculating the various quantities and their cost in the building construction. It is needed for controlling the expenditure during the execution of the work.

3. The process of working out the cost per unit of each item is known as _________
a) Work
b) Sheet
c) Data
d) Analysis

Answer: c
Clarification: The preparation of a detailed estimate comprises of working out quantities of different items of work and then determining the cost of each item. The process of working out the cost per unit of each item is known as data.

4. While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per __________
a) Special Data Book
b) Standard Data Book
c) Special Data Record
d) Specific Data Record

Answer: b
Clarification: While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per the Standard Data Book. However, the rates of labour and materials are obtained from the current standard scheduled of rates.

5. In the case of works which require some special types of equipment, an amount of ______ percent of the estimated cost is given.
a) 1-2
b) 5-9
c) 12-18
d) 16-20

Answer: a
Clarification: In the case of works that require some special types of equipment, an amount of 1-2 percent of the estimated cost is given. While preparing a detailed estimate, it is also important to select a suitable site of work to reduce damage during the loading and unloading of materials.

6. Which of the following is not a method used for preparing approximate estimates?
a) Cubical contents method
b) Unit base method
c) Plinth area method
d) Cylindrical base method

Answer: d
Clarification: There are various methods used for preparing approximate estimates. These are the plinth area method, unit base method and cubical contents method. An approximate estimate is needed for studying various aspects of the work of the project.

7. In the plinth area method, the cost of construction is computed by the multiplication of ________
a) Plinth length and rate
b) Plinth breadth and rate
c) Plinth area and plinth area rate
d) Plinth volume and plinth length rate

Answer: c
Clarification: In the plinth area method, the cost of construction is computed by the multiplication of plinth area and plinth area rate. This area is calculated by multiplying the length and the breadth.

8. As per IS 3861-1966, which of the following areas should not be included while calculating the plinth area of a building?
a) Porches of non-cantilever type
b) Area of barsati at terrace level
c) Area of walls at floor level
d) Area of lofts

Answer: d
Clarification: As per IS 3861-1966, the areas which should be included while calculating the plinth area of a building are porches of non-cantilever type, area of barsati at terrace level, area of walls at floor level, etc. However, the area of lofts should not be included.

9. For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method.
a) True
b) False

Answer: a
Clarification: For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method. Cubical contents method is usually used for multi-storeyed buildings.

10. In the cubical contents method, the cost of a structure is computed by the multiplication of total cubic contents and _______
a) Area of building
b) Volume of building
c) Local cubic rate
d) Length of building

Answer: c
Clarification: The cost of a structure in the cubical contents method is determined by the multiplication of total cubic contents with the local cubic rate. Therefore, the cost of the building is calculated by multiplying the volume of buildings with the rate per unit volume.

Leave a Reply

Your email address will not be published. Required fields are marked *