250+ TOP MCQs on Special Problems in Soil Stabilization Work and Answers

Highway Engineering Multiple Choice Questions on “Special Problems in Soil Stabilization Work”.

1. How many types of challenges are encountered in bitumen stabilisation?
a) One
b) Two
c) Three
d) Four
Answer: c
Clarification: The major problems are choice of stabilisation, design mix and thickness of layer.

2. The final choice of stabilisation technique is based on __________
a) Labour
b) Material
c) Equipment
d) Cost
Answer: d
Clarification: Though all the equipment, labour and materials are equally important, the final factor is cost.

3. The flexural strength is based on __________
a) IRC
b) Plate test
c) CBR
d) Shear
Answer: c
Clarification: The most commonly used method for testing the strength of the flexible pavement.

4. The mix design should take into consideration is?
a) Stability
b) Durability
c) Stability and durability
d) Age
Answer: c
Clarification: The mix should take into consideration, the stability and durability requirements, strength is also equally important.

5. The modification factor used in base course thickness is called __________
a) Granite equivalence
b) Gravel equivalence
c) Sand equivalence
d) Soil equivalence
Answer: b
Clarification: In the thickness of the pavement layer the mix can’t be designed directly, so it needs some factor which is called equivalence factor.

6. The colloidal content in BC soils can be up to __________
a) 20%
b) 30%
c) 40%
d) 50%
Answer: d
Clarification: The colloidal content in the soil may be up 50%, which is an undesirable property for pavement.

7. What is the shrinkage limit value in BC soil?
a) 0%
b) 9%
c) 15%
d) 16%
Answer: c
Clarification: The BC soils have a less shrinkage limit value from 10% to 15 %, which is a very high value, whereas in sand and silt they don’t exist.

8. The cement content required for BC soil is __________
a) High
b) Very high
c) Low
d) Very low
Answer: b
Clarification: The cement content required for the cement is 15 to 25%, so it is not advisable to directly stabilize with cement.

9. The desert sand is __________
a) Strong
b) Weak
c) Normal
d) Unfit for pavements
Answer: b
Clarification: The sand in the desert is very huge and non availability of water is a major problem in the desert, and desert sand is very less stable, hence suitable stabilisation should be done.

10. The water content in the emulsion is about __________
a) 10%
b) 20%
c) 30%
d) 40%
Answer: d
Clarification: The emulsion in the mix consists of 40% of water, hence it is used for stabilisation of desert sand.