Statistical Quality Control Multiple Choice Questions & Answers on “Variable Charts – Control Charts for x̅ and R – 2”.
1. LCL for the R chart is given by __________
a) D3R
b) D2R
c) R – D3R
d) d2R
Answer: a
Clarification: LCL for an R chart is always given by the following equation,
LCL = D3R.
2. In the general equation of UCL of a control chart, for any x chart, which of these is used as the estimator of μ?
a) (bar{x})
b) (bar{R})
c) (bar{bar{x}})
d) (bar{bar{R}})
Answer: c
Clarification: UCL=μ+ Zα/2 σ is the general equation for UCL for any control chart. For any (bar{x}) chart, (bar{bar{x}}) is used as the estimator of μ in the above mentioned equation.
3. Which of these gives the correct value of A2 used in the equation for control limits of a x control chart?
a) (frac{3}{d_2 sqrt{n}})
b) (frac{3}{sqrt{n}})
c) (frac{3}{d_2})
d) (frac{3}{sqrt{d_2}})
Answer: a
Clarification: The value of A2 used in the equation of control limits of a x control chart is given by following equation,
(frac{3}{d_2 sqrt{n}})
4. In phase I application of x and R chart, the control limits obtained from the equations are treated as ____________
a) Final limits
b) Trial limits
c) Warning limits
d) Pattern limits
Answer: b
Clarification: The obtained limits from the equation of control limits for a x and R chart, are generally treated as Trial limits. They allow us to determine whether the process was in control when the m initial samples were taken.
5. Which term is having a closest meaning as Sampling Distributions?
a) Control charts
b) On site inspection
c) Whole lot inspection
d) Acceptance sampling
Answer: a
Clarification: The term “control charts” is having a closest meaning to “sampling distribution” because, control charts are also plotted on the data obtained from the sample inspection and also, they show variation in sample data.
6. Process capability generally uses __________
a) Specifications
b) Control Limits
c) Process standard deviation
d) Mean of any one sample
Answer: b
Clarification: Process capability studies make use of the specifications of any certain Critical-to-quality characteristic or quality characteristic to estimate the performance of any process.
7. The process standard deviation is given by __________
a) R/d2
b) Rd2
c) 1/d2
d) R/d
Answer: a
Clarification: The process standard deviation may be estimated by using the following equation,
(hat{σ} = frac{bar{R}}{d_2})
8. For any process, the sample ranges are, 1.2,1.5,1.1,1.4,1.5. The subgroup size is 5. What will be the process standard deviation? Given: d2=2.326 and A2=0.577
a) 0.576
b) 2.322
c) 0.511
d) 2.463
Answer: a
Clarification: We know that,
(bar{R} = frac{sum_{i=0}^{i=n} R_i}{n}) and “process standard deviation = (frac{bar{R}}{d_2})“, by using the values of R and d2 in the question, we get process standard deviation=0.576
9. A tolerance diagram is also called ____________
a) Scatter diagram
b) Defect concentration diagram
c) Histogram
d) Tier chart
Answer: d
Clarification: The run chart of individual observations in each sample is called the tolerance diagram for any process. The tolerance diagram is also called Tier chart of the process.
10. Is there any relationship between specification limits and control limits of x and R charts?
a) Yes, Specification limits = Control limits
b) Yes, Control limits=Specification limits/2
c) No
d) Yes, Control limits*0.5 = Specification limits